Major Water & Sewer Pipeline Revamp in North Chennai

 

Chennai: North Chennai is set to witness a massive infrastructure upgrade with the replacement of 277 km of aging pipelines under the Vada Chennai Valarchi Thittam (VCVT). The ₹946.42 crore project aims to modernize the city’s water and sewer networks, improving sanitation and preventing frequent disruptions in the water supply.

 

Project Overview

The project involves replacing 157 km of water pipelines and 120 km of sewer lines to address issues caused by 30-year-old pipelines that frequently burst, leaked, or failed to provide sufficient water pressure. The government has allocated ₹231.25 crore for water supply improvements and ₹715.18 crore for sewer system upgrades.

 

Key Developments

Some of the major planned works include:

✅ 1,000mm Cast Iron (CI) pumping main from Elaya Street to Kodungaiyur STP

✅ Strengthening pipelines in Tondiarpet and Kolathur

✅ Upgrading sewer mains in Depot 60 and 64

✅ Setting up a new roadside sewage pumping station at Broadway Road

 

These upgrades are expected to significantly improve sewage collection, prevent overflows, and enhance sanitation in densely populated areas of North Chennai.

 

Need for the Project

The existing pipelines, many over three decades old, have led to:

🚰 Frequent water supply disruptions

🚱 Sewer overflows and pollution

🛑 Low water pressure and defective pipelines

🚧 Collapsed manholes and sewer blockages

 

The replacement project will tackle choked water mains, broken sewer lines, and outdated infrastructure, ensuring efficient water distribution and better sanitation.

 

Implementation & Work Plan

The work has been divided into six packages:

 

Two packages for water pipelines

Four packages for sewer system improvements

Authorities have already issued work orders for Water Package II and Sewer Package IV, and preliminary surveys have begun in the designated areas.

 

Affected Areas & Public Cooperation

The project will benefit thousands of residents across several neighborhoods, including:

📍 Ennore (Area I), Muthumariamman Koil Street (Area III), Washermenpet, Tondiarpet, Royapuram, and Korukkupet (Area IV)

📍 Walltax Road, Thambuchetty Street, Chindatripet, Pudupet, and Seven Wells Road (Area V)

📍 Kolathur, Agaram, Perambur, Aynavaram, Pulianthope, Otteri, Perambur Barracks Road (Area VI)

 

Officials have urged the public to cooperate with temporary disruptions as the work progresses, ensuring a smooth transition to the new, improved water and sewer network.

 

💧 #WaterSupply #ChennaiDevelopment #UrbanSanitation #VCVT #InfrastructureUpgrade

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button
error: Content is protected !!